Dover
Dover Census Data, 2010
May 26, 2011
Census data for the Town of Dover is available on the Dutchess County website, http://www.co.dutchess.ny.us/CountyGov/Departments/Planning/PLcensus.htm
From Kathy Schibanoff, Board of Education President and Dover Knolls Liason: “Attached is the pdf for Dover, and a sheet of census analysis done by Pattern for Progress, a regional think tank. This mirrors what is happening in the schools in the Hudson Valley.”
Dover Planning Board Co-Chair Valerie LaRobardier gets credit for drawing our attention to http://blogs.census.gov/ from whence the following two notes come:
- Read “Demographic Analysis” And The Census
- Read The Release of The 2010 Demographic Analysis Population Estimates
“Demographic Analysis” And The Census
January 22, 2011
From the census.gov blog
There are two principal ways that we try to learn about the size of the US population. One, the decennial census, is the focus of this blog. The other method, called “demographic analysis,” uses the “vital registration” system of the US — birth registrations, death registrations – as well as estimates of immigration and emigration.
Dover Planning Board Meeting June 21, 2010
June 21, 2010
- Read Dover Planning Board Meeting Minutes, June 21, 2010
Dover Planning Board Meeting June 7, 2010
June 7, 2010
- Read Dover Planning Board Meeting Minutes, June 7, 2010
Dover Planning Board Meeting May 17, 2010
May 17, 2010
- Read Dover Planning Board Meeting Minutes, May 17, 2010
Rasco: Dover Planning Board continues Public Hearing, April 19, 2010
April 19, 2010
[Planning Board] Member Johnson- you had valid permits, there was a stop work order, and the permits were taken away and it took 5 years to get permits, that’s not voluntary. If it was voluntary, your permits would have been kept up and the place would have never been shut down for 5 years. You pull your gas tanks out or you can get rid your permits – it sounds like you lost your permits-
Jon Adams- you’re arguing case law- it’s been established from different attorneys.
Member Johnson- But neither of them represents the Planning Board.”
Rasco: Dover Planning Board Meeting March 1, 2010; DEC Director Janeway: “Without local approval, [Rasco] cannot move forward”
March 1, 2010
The Dover Planning Board invited Willie Janeway, Regional Director for NYS DEC Region 3, “to discuss Planning Board concerns with the Howland Lakes site” where the Rasco project is proposed.
From the Minutes:
“Co-Chair Wylock thanked Mr Janeway for responding to his letter, there was a site walk January 16, 2010 and The Board was shocked at the site. There are bags of carbon, barrels of unknown substances, abandoned cars and trucks, and a tent like structure all within proximity of the Great Swamp. It was understood that someone from DEC did visit the site prior to the permit being issued.
[Chair Wylock] was unsure if something was overlooked, if the site was in this condition, or if this was outside the scope of the inspection. He felt that DEC and The Town should work together to get the site cleaned up, before the application moves forward; certainly prior to the Application of Cricket Valley Energy. The Landowner [Howland Lakes] not the applicant should be held accountable; it has the appearance of an environmental nightmare.”
Read further for Mr. Janeway’s response, in which he reminds the Dover Planning Board, “Without local approval, [Rasco] cannot move forward.”
- Read Dover Planning Board Meeting Minutes, March 1, 2010
*Note: printed post date is for chronological clarity. Actual post date is August 13, 2010.
Rasco: Dover Planning Board Meeting February 1, 2010: Legality of Stipulation Agreement is challenged
February 1, 2010
Rasco attempts to submit documents to the Dover Planning Board for the solid waste facility after the Board’s January site visit. “No documents were distributed to the Board as per the policy of having all documents processed prior to distribution.”
Dover Code Enforcement Officer George Hearn recommended the Planning Board get a letter from Jim Napoli, Dutchess County Board of Health, confirming that Rasco’s water and wastewater plans comply with DC BOH regs.
A lengthy discussion follows as to the legality of the Stipulation Agreement: Is Rasco a pre-existing operation?
“[Dover Planning Board Chair] Wylock: The operation was shut down in 2005?
A: Yes.” ….
[Dover Planing Board] Member Kelly: stated he would like to rescind his vote of last month ratifying the agreement with the Planning Board and the Town Board.”
- Read Dover Planning Board Meeting Minutes, February 1, 2010
*Note: printed post date is for chronological clarity. Actual post date is August 13, 2010.
Rasco: Dover Planning Board Meeting, January 6, 2010; Board questions “primitive” plans for accidental petroleum contamination
January 6, 2010
Rasco appears before the Dover Planning Board to discuss the Application for Site Plan Approval. The Board members are surprised to find there are no provisions for a water and wastewater facility. What do Rasco employees do if they get oil on their face? on their hands? “Wipes,” is Rasco’s answer . What if they actually have to use water? Where does the petroleum contaminated water go? “The most sensitive environmental resource is the Great Swamp, which is not really adjacent to this and there should be zero impact. Since there is no water supply there should be only storm water.”
The Rasco Project is proposed for the same parcel as Cricket Valley Energy (CVE,) a 1000 megawatt power plant which is subject to full environmental review under SEQRA. CVE is addressing in detail the environmental impact on the Great Swamp. The Rasco operation next door will bring in and handle Petroleum Contaminated Soil over our singele source aquifer which supplies 20,000 Eastern Dutchess County residents with drinking water, and is not subject to full environmental review under SEQRA?
- Read Dover Planning Board Meeting Minutes, January 6, 2010
*Note: printed post date is for chronological clarity. Actual post date is August 13, 2010.


